Nāʻālehu Interim disaster housing

The Hawaiʻi Department of Human Services (DHS) is providing 12 interim homes beside the Nāʻālehu Public Library for individuals and families displaced by Hurricane Lala. All 12 homes are now on island. The latest update and the public comments received are posted below.

  • Homes delivered 12 of 12 on island Site work and utilities underway
  • Key ceremony Friday, December 18 Target date; depends on weather and the HECO grid connection
  • Public comments 6 received, Oct 6 to 20 Compiled and posted below

Status as of October 30, 2026

Project12 two-bedroom, one-bath interim homes for households displaced by Hurricane Lala
LocationNāʻālehu Civic Center (State land), 95-5669 Māmalahoa Hwy, beside the public library
Homes delivered12 of 12 on island
Applications10 pre-applications received; 7 eligible for consideration, with 1 additional household to apply (County of Hawaiʻi)
Key ceremonyFriday, December 18, 2026

From the DHS legislative update dated October 30, 2026. Read the full update (PDF, 2 pages).

October update

  • Site work. Civil plan finalized October 14; excavation and site utilities installation underway. Basalt rock closer to the surface than expected slowed excavation and has pushed the occupancy-ready date from October 30 to December 18. The schedule also depends on weather.
  • Homes. 12 of 12 are on island.
  • Power. HECO will extend service from Māmalahoa Highway with one new pole, which may require removing one tree and trimming another; every effort to avoid this has been explored. DHS is seeking Library, DAGS and community agreement first.
  • Permits. Updated drawings are moving through the County's EPIC system, with fire, water and health coordination ongoing.
Two photos: an excavator working beside the library, and a trench showing dark basalt rock near the surface.
Excavation beside the library (left) and basalt rock near the surface (right), October 2026. From the DHS update.

What the community said

Residents weighed in at the October 8 meeting and in written comments through October 20. Two major themes emerged, and the project team is addressing each:

  • Traffic on Māmalahoa Highway. Traffic calming is being raised with the Department of Transportation.
  • Room for the library to grow. Several comments supported the project but asked that space be preserved for future library expansion. The existing septic leach field directly behind the library presents site constraints that may limit expansion.

Additional outreach was held Monday, October 26, at Nāʻālehu Hongwanji, and talk-story sessions with families staying in hotels are planned. The Library and Civic Center will be notified before the November 10 to 13 crane work, with a DOT public notice when the homes are trucked in and for ironwood tree removal and pruning.

Public comments received

Six written comments were received between October 6 and October 20, 2026. They are compiled in one document, in the order received and reproduced as submitted, including original spelling and emphasis.

  • Support for the project and the expedited timeline
  • Technical requirements and local prefab supplier opportunities
  • Concerns about the site, cost and eligibility
  • Site design to allow future library expansion
  • Support for the revised design
  • Application form issue and Punaluʻu water service

Personal contact information, including email addresses, phone numbers, mailing addresses and handwritten signatures, has been redacted from the compilation. Attachments referenced in a comment, such as videos or forms, are not included. Read the comment policy.

About the project

DHS is providing 12 two-bedroom, one-bath interim housing units for eligible individuals and families displaced by Hurricane Lala. The homes provide temporary, safe housing while households work toward securing permanent housing. The proposed budget includes one year of housing, utilities and maintenance at no cost to residents.

Because available units are limited, the County of Hawaiʻi determines eligibility and prioritizes applicants based on housing needs and vulnerability. After their use as disaster housing, the homes are intended to serve as interim workforce housing for educators and clinicians.

A single-story modular home with wood siding, a small front deck and landscaping.
One of the two-bedroom units. Photo from the DHS project brief.
Aerial rendering of the site plan: 12 numbered units in two rows behind the Nāʻālehu Library, off Māmalahoa Highway.
Current site layout: 12 units beside the Nāʻālehu Library, off Māmalahoa Highway. The layout was designed to foster a sense of community and make efficient use of the land within existing site constraints. Tap the image to see it full size.

Homes for daily living

Each unit includes queen-size beds, closet space, ceiling fans and air conditioning; a refrigerator and stove with oven; a full-size shower and a washer/dryer.

Displaced by Hurricane Lala? You can still reach out

The County has received fewer eligible applications than there are homes, and outreach continues to reach displaced families, especially those staying in hotels or who have relocated outside Kaʻū. Pre-applications go to the County of Hawaiʻi, which determines eligibility and conducts background checks.

  • Online

    Complete the online pre-application on the County of Hawaiʻi website.

  • Download and email or drop off

    Download the pre-application form, complete it, and email or drop off the form as instructed on the form.

The original pre-application deadline was October 25, 2026. If you know a displaced household that has not applied, please refer them to the County or email input@communityvoice.net and we will help connect them.

Project timeline

Updated November 10, 2026, from the DHS update of October 30. Basalt rock near the surface added several weeks of excavation, moving the target from October 30 to December 18.

  1. September 14 to October 5Land clearing and rough grading. Civil and structural design. Units prepared and shipped from Lahaina.
  2. October 8Community meeting at the Nāʻālehu Public Library. Written comments accepted through October 20.
  3. October 14Civil plan finalized.
  4. Weeks of October 19 and 26Units arrive at Hilo Harbor; all 12 on island by October 30. Excavation and site utility installation, slowed by basalt rock near the surface. Outreach session at Nāʻālehu Hongwanji on October 26.
  5. November 10 to 13Crane work; homes trucked to the site. DOT public notice for the move and for ironwood tree removal and pruning.
  6. November and early DecemberHECO service extension from Māmalahoa Highway, utility connections, permits through the County's EPIC system, and site finishing.
  7. Friday, December 18Target ready-for-occupancy date and key ceremony.

This schedule remains tentative and is subject to change based on weather, site conditions, and HECO's connection to the electrical grid. Updates will be posted here as milestones are reached.

Questions about the project

The formal comment period closed on October 20, 2026, and the comments received are posted above. Questions and referrals are still welcome by email.